Last week it's been a hot week on KOMO site, which has pushed the overoofing work of the last senior blocks. Our builders on site are building two single-level Senior Blocks with overroofs, one is  7 units a row in two parellel rows, the other 4 units a row in two parellel rows, which is generally lower than the former block. So the overroofing between the two blocks became more complicated. Thanks to the flexibility of the modular units, the builders welded some connection blocks above the lower block end unit so the deck between the two blocks is leveled.
The deck turns out to be good-looking. Actually we could come up with a better solution for the deck overroof, putting 3 spare roofs on the top of the deck so it's got ceiling panels.
In addition, another row of 11 senior units have been on the foundations parellelly in front of the above two blocks.
The Contractor has already started the construction of the Termianl buildings for the airport, putting the GeoFabric layer on the bottom of the foundations firstly.

------分隔线----------------------------